The Transform(ation) is beginning (see what I did there?)

On Monday, March 18th we met with an engineering technician to map out what was needed for the electrical service upgrade.

Currently we have single phase service going to the northeast corner of the warehouse.  There are two  meters.  We believe one is for the warehouse and one is for the house (but we'll need to confirm this).



If the upgraded service goes to this same location, we will have significant expense to run power to the southwest side of the building where the chiller will go.  We were hoping, best case, to get service to the northwest corner of the building to reduce the distance we need to run wires (especially the larger more expensive wires that are needed for the 400 amp service).  Essentially, the thinking was, bring 600 amp service to the northwest corner of the building, backfeed 200 amps to the existing box and run 400 amps to the chiller.

Turns out that AEP is considering putting a transformer on a pad just next to where the chiller will go!  This should save us some significant expense.The remaining question is whether we can leave the existing service like it is (separate) and just put 400 Amp service by the chiller or whether we will still need to backfeed the existing panel (add 600 Amp service and backfeed 200 Amps to the panel).

We are hoping since the building is currently single phase and the chiller needs 3 phase that we can have them separate and save us some additional expense.  Keep your fingers crossed!