Progress Continues
Work is continuing at the club. Progress is being made. Haven't had time between work and club commitments to make any posts lately. But here is where we stand and what is coming up. The catwalks are nearly complete and the north and south walls of the ice room have been painted white. There is a little more work to be done on the east catwalk, but after that the ice equipment install needs to be completed before the rest of the catwalks can be built. The HVAC Contractors have made significant progress with the old A/C and heaters removed, the new heaters and ductwork up, and the Dehumidifier hung: We ran into one challenge upon speaking with the fire marshal. Specifically, we will need to add smoke detectors above the low-e ceiling (as well as below it) because the low-e ceiling does not go wall to wall. This will cost us an additional $5k and will take another week to get completed. We have the cables for the low-e ceiling mounted and are just waiting fo