The catwalks have begun!

Image
Progress continues. After the demolition last week, the new ADA Changing Room, Kitchen and Beer Cooler have been framed out. And drywalling has begun.  Just one side so far until the final electrical inspection occurs which should be within the next week or so.  Also, very importantly, the chiller successfully made the move over from the old club.  On Saturday this weekend, a regular cadence of work at the facility has begun.  We are looking at working 3 days per week (Saturday 9 am - 3 pm, Monday nights 5:30 pm - 9:00 pm, and Wednesday nights 5:30 pm - 9:00 pm). We have about 6 weeks to get the dehumidifier, heaters, duct sox, lights, low-e ceiling, ice room painting, catwalks and sealing of the pond completed before Jim Hibbard arrives mid-July for the ice mat installation. Saturday's work Andrew Nottingham continued the work of dusting the joists.  Andrew and Andy Downs have been working their way through the warehouse.  The goal is to reduce the p